Cooling Tower Performance Assessment
Review water temperatures, flow, entering wet-bulb temperature and operating conditions.
We take readings at your site and explain what the results mean, so your team can plan maintenance or decide whether an upgrade is worth pursuing.
Request a Quotation
Review water temperatures, flow, entering wet-bulb temperature and operating conditions.
Agree the traverse locations and measurement method before calculating airflow.
Review fan condition, speed and electrical readings as agreed.
Take point readings over an agreed plane and document measurement conditions.
Record water temperatures and flow using agreed measurement points and methods.
Review accessible parts and record findings alongside the operating data.
Document methods, observations, assumptions and recommended actions within the agreed scope.
PERFORMANCE ASSESSMENT
Agree measurement points, instruments, duration and test conditions before work begins, so the findings answer the project’s actual questions.
Hot-water inlet − cold-water outlet temperature
Cold-water outlet − entering-air wet-bulb temperature
Calculated from water flow and temperature difference
Actual power measurement (kW) within the agreed scope
Agree the method, measurement points, instruments and assessment criteria before testing. Before-and-after comparisons consider load, flow, weather and controls. Airflow testing alone does not establish thermal performance. Site reports are not third-party certification unless included in the agreement.